Project: Large UK Data Centre, Cardiff

24/7, 365 days a year response

Response for UK is within 4 hours

Large UK Data Centre, Cardiff

  • Replacement 2x 1300kW Air cooled machines, Pumps, controls and electrical infrastructure on a critical LIVE datacentre

Challenges:

  • Working within one of the most critical UK LIVE datacentre environment; this call centre belongs to the UK largest Telecoms company and is arguably the single most critical site.
  • We replaced 3x chillers, 2x dry coolers, 10 pumps and 48 CRAC units without 1x single disruption to services or incident for entire duration of project

    CLIENTS

    Latest News

    Project: Data Centre, London Docklands

    Project: Data Centre, London Docklands

    24/7, 365 days a year response Response for UK is within 4 hoursData Centre, London Docklands Replacement 4x 1200kW Turbocor machines, Pumps, controls and electrical infrastructure on a critical LIVE datacentre Challenges: Working within a LIVE datacentre environment...

    Project: 41mW Battery Storage Centre

    Project: 41mW Battery Storage Centre

    24/7, 365 days a year response Response for UK is within 4 hours41mW Battery Storage Centre, Birmingham Critical close control temperature and humidity N+1 system. TRANE Indoor air cooled chillers, 6x battery room AHUs, mechanical and electrical services. 150m3/hr...

    Address

    Unit 2, Great Western Place Station Road, Burlescombe, Tiverton, Devon, United Kingdom, EX16 7GW.

    Sitemap

    Phone

    01823  662330

    Follow Us